RUPERT ST, BRISTOL - GREYFRIARS FOOTBRIDGE DEMOLITION

 

 

 

Operating as contractors for RC Demolition (Wring Group), TR Services designed and assisted in the erection and installation of support towers for the Greyfriars footbridge demolition, in Rupert Street, Bristol.

Three 6.5 metre support towers, constructed using RMD kwikform equipment were constructed to provide support to the footbridge during controlled demolition.

Due to a 6 metre wide culvert underneath the road, channelling the River Frome through Bristol city centre, loadings transmitted from the bridge through each tower to the road were calculated to ensure load distribution did not threaten the integrity of the culvert or the road.

The three RMD kwikform towers were erected at the Wring Group's premises and then transported to Rupert street, where they were installed and linked together underneath the bridge.

The bridge was then demolished.

 

 

 
   

 

The end product.

 

 
 
 
 