Services were contracted to provide temporary propping to
permit a major column replacement programme to be undertaken.
The illustration below shows how 3D graphics were used to
illustrate, prior to contract realisation, how a concrete
floor slab was to be supported whilst allowing access to the
column at the same time. RMD Kwikform Megashor props and beams
were utilised to provide the primary support and Megashor
props were then installed down through each floor as back
propping. The design load through the propping system was
210 tonne.